A) A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV) ,then discounting the TV at the WACC.
B) A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV) ,then discounting the TV to find the IRR.
C) If a project's IRR is smaller than the WACC,then its NPV will be positive.
D) A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost.
E) If a project's IRR is positive,then its NPV must also be positive.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 15.00%
B) 12.83%
C) 16.67%
D) 13.33%
E) 20.66%
Correct Answer
verified
Multiple Choice
A) You should reject both projects because they will both have negative NPVs under the new conditions.
B) You should delay a decision until you have more information on the projects,even if this means that a competitor might come in and capture this market.
C) You should recommend Project L,because at the new WACC it will have the higher NPV.
D) You should recommend Project S,because at the new WACC it will have the higher NPV.
E) You should recommend Project L because it will have both a higher IRR and a higher NPV under the new conditions.
Correct Answer
verified
Multiple Choice
A) 0$222.13
B) 0$185.11
C) 0$157.34
D) 0$174.00
E) 0$198.07
Correct Answer
verified
Multiple Choice
A) If a project with normal cash flows has an IRR greater than the WACC,the project must also have a positive NPV.
B) If Project A's IRR exceeds Project B's,then A must have the higher NPV.
C) A project's MIRR can never exceed its IRR.
D) If a project with normal cash flows has an IRR less than the WACC,the project must have a positive NPV.
E) If the NPV is negative,the IRR must also be negative.
Correct Answer
verified
Multiple Choice
A) 9.64%
B) 10.82%
C) 12.58%
D) 11.29%
E) 11.76%
Correct Answer
verified
Multiple Choice
A) If Project A has a higher IRR than Project B,then Project A must have the lower NPV.
B) If Project A has a higher IRR than Project B,then Project A must also have a higher NPV.
C) The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC.
D) The IRR calculation implicitly assumes that cash flows are withdrawn from the business rather than being reinvested in the business.
E) If a project has normal cash flows and its IRR exceeds its WACC,then the project's NPV must be positive.
Correct Answer
verified
Multiple Choice
A) You should recommend that the project be rejected because its NPV is negative and its IRR is less than the WACC.
B) You should recommend that the project be rejected because,although its NPV is positive,it has an IRR that is less than the WACC.
C) You should recommend that the project be accepted because (1) its NPV is positive and (2) although it has two IRRs,in this case it would be better to focus on the MIRR,which exceeds the WACC.You should explain this to the president and tell him that that the firm's value will increase if the project is accepted.
D) You should recommend that the project be rejected because (1) its NPV is positive and (2) it has two IRRs,one of which is less than the WACC,which indicates that the firm's value will decline if the project is accepted.
E) You should recommend that the project be rejected because,although its NPV is positive,its MIRR is less than the WACC,and that indicates that the firm's value will decline if it is accepted.
Correct Answer
verified
Multiple Choice
A) A project's MIRR is always greater than its regular IRR.
B) A project's MIRR is always less than its regular IRR.
C) If a project's IRR is greater than its WACC,then the MIRR will be less than the IRR.
D) If a project's IRR is greater than its WACC,then the MIRR will be greater than the IRR.
E) To find a project's MIRR,we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC.
Correct Answer
verified
Multiple Choice
A) 12.69%
B) 13.98%
C) 15.58%
D) 18.15%
E) 16.07%
Correct Answer
verified
Multiple Choice
A) 2.61 years
B) 1.97 years
C) 2.42 years
D) 2.26 years
E) 2.38 years
Correct Answer
verified
Multiple Choice
A) -$47.38
B) -$39.09
C) -$29.61
D) -$40.27
E) -$39.48
Correct Answer
verified
Multiple Choice
A) The longer a project's payback period,the more desirable the project is normally considered to be by this criterion.
B) One drawback of the payback criterion for evaluating projects is that this method does not properly account for the time value of money.
C) If a project's payback is positive,then the project should be rejected because it must have a negative NPV.
D) The regular payback ignores cash flows beyond the payback period,but the discounted payback method overcomes this problem.
E) If a company uses the same payback requirement to evaluate all projects,say it requires a payback of 4 years or less,then the company will tend to reject projects with relatively short lives and accept long-lived projects,and this will cause its risk to increase over time.
Correct Answer
verified
Multiple Choice
A) An NPV profile graph shows how a project's payback varies as the cost of capital changes.
B) The NPV profile graph for a normal project will generally have a positive (upward) slope as the life of the project increases.
C) An NPV profile graph is designed to give decision makers an idea about how a project's risk varies with its life.
D) An NPV profile graph is designed to give decision makers an idea about how a project's contribution to the firm's value varies with the cost of capital.
E) We cannot draw a project's NPV profile unless we know the appropriate WACC for use in evaluating the project's NPV.
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) 14.93%
B) 10.00%
C) 12.04%
D) 13.97%
E) 9.15%
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) The NPV method was once the favorite of academics and business executives,but today most authorities regard the MIRR as being the best indicator of a project's profitability.
B) If the cost of capital declines,this lowers a project's NPV.
C) The NPV method is regarded by most academics as being the best indicator of a project's profitability,hence most academics recommend that firms use only this one method and disregard other methods.
D) A project's NPV depends on the total amount of cash flows the project produces,but because the cash flows are discounted at the WACC,it does not matter if the cash flows occur early or late in the project's life.
E) The NPV and IRR methods may give different recommendations regarding which of two mutually exclusive projects should be accepted,but they always give the same recommendation regarding the acceptability of a normal,independent project.
Correct Answer
verified
True/False
Correct Answer
verified
Showing 41 - 60 of 107
Related Exams